PRINCE2 7 Practitioner Practice Questions
Last updated on .
Free Practice Questions & Answers
These are original practice questions designed to help you review PRINCE2 7 Practitioner concepts.
A project board wants a clear view of whether continued investment in a project is justified. Which PRINCE2 management product provides this ongoing justification?
- Issue Register
- Business Case
- Daily Log
- Quality Register
Reveal Solution
The Business Case explains the expected benefits, costs, risks, and reasons for continuing the project.
During a stage, the project manager forecasts that time tolerance will be exceeded. What should the project manager do first?
- Continue work and report at stage end
- Raise an exception report to the project board
- Change the project plan without approval
- Close the project immediately
Reveal Solution
An exception report escalates a forecast breach beyond agreed tolerance so the project board can decide the next action.
Which role is accountable for ensuring that the project remains desirable, viable, and achievable from the business perspective?
- Senior User
- Executive
- Senior Supplier
- Project Support
Reveal Solution
The Executive owns the Business Case and is accountable for the project’s overall success.
A team manager needs to know the required quality criteria, tolerances, and delivery dates for a specialist product. Which management product should they use?
- Work Package
- Project Brief
- End Stage Report
- Lessons Report
Reveal Solution
A Work Package authorizes and defines work to be completed by a team manager.
Why does PRINCE2 recommend managing by stages?
- To remove the need for project controls
- To give the project board planned points for decision-making and control
- To ensure every project has exactly five stages
- To avoid producing a Business Case
Reveal Solution
Stages provide review and authorization points, allowing the project board to confirm continued justification before committing further resources.