A project team member is struggling with development work, and no other qualified staff are available. What should the project manager do?
Reveal Solution
Training addresses the team member’s capability gap while retaining the available resource.
A junior project manager asks how to improve efficiency and reduce rework. What should the senior project manager recommend?
Reveal Solution
A WBS organizes scope into manageable work packages and supports a realistic schedule based on project and resource needs.
A strong delivery team is working in an unfamiliar domain and is not meeting expectations. What should the project manager do?
Reveal Solution
Supporting the team to identify the missing knowledge or skills directly addresses the cause of the performance gap.
On an agile project in a changing business environment, the sponsor is concerned about benefits realization. How should the project manager keep the product valuable?
Reveal Solution
Regular backlog reprioritization allows the team to focus on the work that continues to provide the greatest business value.
While the project manager is temporarily away, the team develops a detailed schedule. On returning, the project manager finds it nearly complete. What should the project manager do?
Reveal Solution
The schedule should be reviewed for alignment with approved project objectives before it is finalized.