Question #1Topic: Team development

A project team member is struggling with development work, and no other qualified staff are available. What should the project manager do?

  • A. Assess the person’s development needs and arrange suitable training
  • B. Use budget reserves to hire a replacement immediately
  • C. Ask the functional manager to offer an incentive
  • D. Request a more skilled replacement
Reveal Solution
Correct Answer: A
Training addresses the team member’s capability gap while retaining the available resource.
Question #2Topic: Planning and rework

A junior project manager asks how to improve efficiency and reduce rework. What should the senior project manager recommend?

  • A. Build a schedule from the project and resource requirements using a work breakdown structure
  • B. Require everyone to work eight hours daily
  • C. Assign tasks without considering team skills
  • D. Hold daily stakeholder meetings to review the plan
Reveal Solution
Correct Answer: A
A WBS organizes scope into manageable work packages and supports a realistic schedule based on project and resource needs.
Question #3Topic: Team capability

A strong delivery team is working in an unfamiliar domain and is not meeting expectations. What should the project manager do?

  • A. Help the team identify and address its development gap
  • B. Dissolve the team
  • C. Remove the members who are struggling
  • D. Demand the same output as in past projects
Reveal Solution
Correct Answer: A
Supporting the team to identify the missing knowledge or skills directly addresses the cause of the performance gap.
Question #4Topic: Agile value delivery

On an agile project in a changing business environment, the sponsor is concerned about benefits realization. How should the project manager keep the product valuable?

  • A. Change iteration objectives whenever a stakeholder requests it
  • B. Stop every iteration when an external change occurs
  • C. Reprioritize the backlog after each iteration to reassess business value
  • D. Use pair programming as the main change-control method
Reveal Solution
Correct Answer: C
Regular backlog reprioritization allows the team to focus on the work that continues to provide the greatest business value.
Question #5Topic: Schedule alignment

While the project manager is temporarily away, the team develops a detailed schedule. On returning, the project manager finds it nearly complete. What should the project manager do?

  • A. Check that the schedule aligns with the project vision and objectives
  • B. Escalate the team to the PMO
  • C. Move straight to execution without review
  • D. Discard the schedule and start over
Reveal Solution
Correct Answer: A