PMP PMBOK 8 Free Practice Questions and Answers

in PMI

PMI PMP PMBOK 8 Practice Questions

Last updated on Oct 31, 2026.

677 Questions & Answers

Continue with free PMP and PMBOK 8 practice questions and answers covering project delivery, team leadership, and stakeholder collaboration. Select Reveal Solution after choosing your answer.

Question #6Topic: Hybrid approach

An organization has only predictive-project experience, but a complex research project has significant uncertainty. How can the project manager build support for a hybrid approach?

  • A. Notify the team that hybrid will be used
  • B. Send a request letter only to the PMO
  • C. Create a change request before stakeholder discussion
  • D. Present the benefits of the hybrid approach to key stakeholders
Reveal Solution
Correct Answer: D
Explaining the approach and its benefits helps stakeholders understand and support a suitable delivery strategy.
Question #7Topic: Knowledge transfer

Subject matter experts have captured process deviations during client knowledge transfer but have not shared them with the project team. What should the project manager do?

  • A. Wait until project closure to discuss lessons learned
  • B. Warn the client that the go-live date may slip
  • C. Ask the PMO to resolve every deviation
  • D. Have the SMEs place the knowledge-transfer documents in the PMIS for the whole team
Reveal Solution
Correct Answer: D
Making the documents available in the project information system shares knowledge with the full team promptly.
Question #8Topic: Resource continuity

A long project depends on highly skilled permanent staff, but turnover could affect delivery. Which two actions help mitigate the risk?

  • A. Split the project into smaller projects
  • B. Hire third-party staff despite the agreed staffing plan
  • C. Build team capability through training, mentoring, and coaching
  • D. Train additional staff as backups
  • E. Start a recognition program
Reveal Solution
Correct Answer: C and D
Developing current staff and preparing additional trained resources reduces the impact of turnover.
Question #9Topic: Team development stages

A multicultural project team remains in the storming stage, cooperation is poor, and the schedule is slipping. What can help the team move toward norming?

  • A. Plan social activities that build relationships and reveal shared goals
  • B. Apply discipline to the members seen as causing problems
  • C. Replace the team
  • D. Show the schedule impact and ask everyone to ignore differences
Reveal Solution
Correct Answer: A
Relationship-building and shared goals help team members develop trust and move toward more collaborative norms.
Question #10Topic: Sprint goal

During a sprint, developers want to leave the highest-priority backlog item and work on unrelated refactoring. What should the project manager do?

  • A. Allow the change and defer discussion to the retrospective
  • B. Reinforce the need to focus on the sprint goal
  • C. Escalate the developers to their functional managers
  • D. Praise the change and ignore the sprint backlog
Reveal Solution
Correct Answer: B
The team should stay focused on the agreed sprint goal; other work can be assessed through the normal backlog process.